HOUSTON (KTRK) -- Drivers and business owners along Kirby have possibly two more miserable years worth of construction headaches because of a design error. We're talking about the stretch of Kirby between Bissonnet and Highway 59.
The Kirby re-construction is a four-phase process. Phases one through three are basically going according to schedule. But phase four is a problem. Though work on the final phase isn't scheduled for a while, we've learned the process is getting delayed even more.
Construction on Kirby near the Rice Village may be inconvenient, but at least it's underway. A few blocks north near Bissonnet and Kirby, the construction timeline is about to get pushed back.
"You always wish things were planned better," said Ron Pickett, who owns Charisma Car Wash.
Pickett and owners of several neighboring businesses just learned that the contractor who did the street survey for the city made a major measuring mistake. To complete the Kirby reconstruction, the city will now need to take 15 feet of his property along the curb line."It makes me feel very nervous because it will be highly detrimental to my business," he said.
The city will now split up phase four of the project into two parts. The portion south of Bissonnet will go on as scheduled with no delays. However, the area north of Bissionnet needs to be redesigned, and that could take a while.
"We'll continue to maintain it and patch it, but we'll redesign it to take into account the additional right of way," said Houston city councilmember Anne Clutterbuck.
Clutterbuck says besides the car wash, the city might need strips of land from Helfman River Oaks and Goode Company Barbecue, businesses that are hoping the delay would result in a compromise that won't take so much of their land.
"Parking's already at a premium and our type of business, we depend on every parking space we have to make ends meet for us and make it work," said Levi Goode with Goode Company.
On Wednesday afternoon, I spoke on the phone with Brown and Gay engineers, the company contracted to do the design work for Kirby. A project manager there told me that historical city records showed the city owned enough land for the Kirby project and no one knew it was a problem until earlier this year.
(Copyright ©2009 KTRK-TV/DT. All Rights Reserved.)
houston traffic, miya shay
- Report a typo
-
Sponsored Content
Advertisement
- Man in wheelchair fatally struck in Pasadena
- Record 2.1 million recall for dropside cribs
- Millions of tax dollars promised for art are misused
- Dozens of rail cars derail in southwest Houston
- Family says slain suspect was suicidal
- Police: O'Quinn driving twice the limit in fatal crash
- Schieffer out; White considering governor run
- Travel websites for Thanksgiving
- ABC says it has received complaints on Adam Lambert
- Surveillance video released after alleged assault
-
Most Popular
-
Most Viewed StoriesMost Viewed VideoMost Viewed Photos
Advertisement
ABC13 Everywhere
Wireless
Breaking news as it happens. Sign up now!
Visit our mobile site at abc13now.com.
Get our iPhone application.
Newsletters, Alerts, and RSS
Sign up for our newsletters to get news, weather and other alerts via email.
Get breaking news alerts on your desktop
With our RSS feeds, get real-time updates of abc13.com using your favorite news reader.
Follow us on Twitter!
Contests, Promotions, and Registration
Check out our contests and promotions. There are always great opportunities to win!
Become a member to enter contests, comment on stories, receive newsletters, and more!
Advertisement
- abc13.com home
- Site Map
- RSS
- Advertise with Us
- Contact Us
- DTV Reports
- Technical Help
- ABC.com
- ABCNews.com
- Privacy Policy
- Safety Information for this site
- Terms of Use
- Copyright ©2009 ABC Inc., KTRK-TV/DT Houston, TX. All Rights Reserved.